BIF ACT SERIES - CHAPTER 3 PROGRESS PAYMENTS - BACK TO BASICS ADJUDICATION - #6

May 13, 2019

The hierarchical nature of construction contracts makes contracted parties extremely vulnerable to the whims and solvency of the contracting parties. Each contractor/subcontractor down the contractual chain will have had to expend substantial resources to carry work out before they are entitled to be paid. A slow paying or insolvent principal or head contractor can be financially devastating for the head contractor or subcontractor respectively. The problem was well summarised by the Cole Royal Commission into the Building and Construction Industry in the early 2000’s, where it was said that security of payment was seen as:

an issue that critically affects the ability of participants in the industry to make a living, and to be rewarded for work that they have performed…hardship [is] caused to subcontractors by builders who are unable or unwilling to pay for work from which they have benefited. The subcontractors who experience payment problems are often small companies or partnerships. Frequently they do not have the expertise or resources to enforce their legal rights, because enforcement would require protracted litigation against much better resourced and more sophisticated companies. Consequently, subcontractors that have operated profitably and well for many years can be forced into liquidation through no fault of their own, often with devastating consequences for the owners of these businesses, their families, their employees and the creditors”.

Although that commentary focussesupon subcontractors, the same can be said for head contractors in the contextof their relationship with principals/owners and sub-subcontractors in thecontext of their relationship with subcontractors immediately above them in thecontractual chain. The political impetusto protect subcontractors through modern security of payment legislation firstappeared in New South Wales in 1999 with the State Government enacting the Building and Construction Industry Securityof Payment Act 1999, which was based upon legislation enacted in the UnitedKingdom in 1996. Within 10 years after the New South Wales legislation began,every State in Australia as well as Singapore and New Zealand had enactedlegislation with the same purposes, although there emerged some significantdifferences between the legislation enacted in some of the States andTerritories. The importance of the system and the desirefor more consistency between the States and Territories was highlighted in whathas become known as the “Murray Report” which is the result of a review ofsecurity of payment laws in Australia undertaken by Mr John Murray AM at thebehest of the Federal Government.

No matter what you think of it, security of payment legislation is designed to facilitate cash flow in the construction industry, down the contractual chain for contractors, subcontractors and suppliers and it has become the primary alternative (payment) dispute resolution mechanism.

Statistics show the majority of claimants succeed in their adjudication applications, at least to some extent. However, there is no presumption in favour of claimants. It is up to the claimant to prove their case to the adjudicator. Even if the respondent has failed to provide a payment schedule in response to the payment claim, or an adjudication response there is still no presupposition that the amount is owing. Put simply, the onus is no less on the claimant to prove their claim to the adjudicator than it is on the respondent to prove their reasons for not paying it.

Welcome to round 6 in our series of articles discussing the basics of adjudication under the Building Industry Fairness (Security of Payment) Act 2017 (“BIF Act”). This instalment discusses the adjudication application. There is a great deal to discuss about adjudication applications so this topic will extend over a couple of instalments.

So far, the articles in our ‘Back to Basics’ series have covered the following:

  • #1 - What is a construction contract, what is a payment claim and what is a paymentschedule;
  • #2 - What is a business day, what is effective service of documents;
  • #3 – What is a reference date;
  • #4 - Key timeframes under the BIF Act for an adjudication application and adjudicationresponse; and
  • #5 - What is the due date for payment.

If you have missed any of the above,or are interested in any of the other current changes facing the constructionindustry, you can view our recent articles here.

As always, those words that appear in italicsin these articles have special meaning. In most cases they will be words orphrases that are specifically defined in the BIF Act.

Adjudication Application

Section 79 of the BIF Act prescribes the statutory requirements for a valid adjudication application namely:

  1. An Adjudication application
  1. must be in the approved form; and
  2. must be made within —
  1. for an application relating to a failure to give a payment schedule and pay the full amount stated in the payment claim—30 business days after the later of the following days—
  1. the day of the due date for the progress payment to which the claim relates;

  1. the last day the respondent could have given the payment schedule under section 76; or
  1. for an application relating to a failure to pay the full amount stated in the payment schedule—20 business days after the due date for the progress payment to which the claim relates; or
  1. must identify the payment claim and the payment schedule, if any, to which it relates; and

  1. must be accompanied by the fee prescribed by regulation for the application; and

  1. may include the submissions relevant to the application the claimant chooses to include.

Looks like a foreign language? Don’tworry, we will translate it for you.

In order for an adjudication application to be valid, you must:

  1. Complete the Form S79 – Adjudication Application (“Application Form”) either on-line on the QBCC website (accessible here) or by downloading and completing a hard copy found on the QBCC website (accessible here).
    Ensure you complete all parts of the Application Form and identify the correct legal entity as both the
    claimant
    and
    respondent
    .
    Identifying the correct entity.
    Identifyingthe correct entity is critical. Where there is no written contract, it can bedifficult to identify the parties to the contract, agreement or otherarrangement as the
    BIF Act
    defines. Insome examples we have seen, one or both of the parties don’t even understand orappreciate who they are contracting with. This can lead to serious consequencesfor the creditor when it comes to trying to recover payment. Where you have purchase/work orders, ortransactions identifying an entity, it will presumedly be the name on thatdocument. However, the most reliable source of information to properly identifya party is the ABN.
    Identifying the wrong entity can be fatal to your application and not only cost you time and money (including the adjudicator’s fees) but could also mean you lose your rights to pursue that claim under the
    BIF Act
    .
    Here are somecommon examples:
  • You do most of your dealings with John Builder but when John asked you to do the job, you received a purchase order or contract from John’s company, 123 Build Pty Ltd, which you accepted and then carried out the work. John Builder is the sole director of 123 Build Pty Ltd. Although John is the sole director of the company, a registered company has its own legal identity. Therefore, the correct entity to serve the payment claim and the adjudication application upon, is 123 Build Pty Ltd. To be sure, always check the ABN on the purchase order or the contract. There is a handy free service available here. If the purchase order or contract does not show the ABN of the person or company engaging you to carry out the work, demand that it be properly put on the purchase order or contract, before your do any work.
  • You enter into a contract with Jane Smith t/as ABC Constructions. ABC Constructions is a registered business name. A business name does not attract legal standing. Consequently, you must commence adjudication against Jane Smith t/as ABC Constructions and not ABC Constructions. Again, check the ABN.
  • You are a second-tier subcontractor in a major development. The developer is XYZ Developers Pty Ltd. The head contractor is 987 Builders Pty Ltd. You are engaged by Bob the Builder Pty Ltd, a subcontractor to 987 Builders Pty Ltd, to perform the window installation. You are aware 987 Builders Pty Ltd are not paying Bob the Builder Pty Ltd for the claimed portion of the window installation work performed, consequently, Bob the Builder Pty Ltd fails to give you a payment schedule and pay the claimed amount on time. Even though there are payment issues between 987 Builders Pty Ltd and Bob the Builder Pty Ltd, you must commence adjudication against your contracting party, Bob the Builder Pty Ltd.
  • You enter into a contract with Jeremiah Johnson, a person you know to be a developer, to construct a number of townhouses. When filling out the contract, Jeremiah says his company is Mountain Pty Ltd and gives you the ABN. You search the and find out it belongs to the Johnson Family Trust. It is important to know whether the organisation you are contracting with is Mountain Pty Ltd in its own right or in its capacity as the trustee of the Johnson Family Trust. This is one situation where searching the ABN details alone won’t necessarily help you. That link we provided above will only identify the name of the trust, not the trustee. A trust on its own is not capable of entering into contracts. It can only do that through a trustee. In this scenario, ask Jeremiah to provide evidence of the identity of the trustee of the Johnson Trust. Then you can be sure when you serve a payment claim and make an adjudication application that the party is correctly identified. For example, Mountain Pty Ltd as trustee for the Johnson Family Trust ABN 12 345 678 901.
  • If your claim is against a Queensland Government department, the respondent should be named as ‘The State of Queensland acting through the Department …………..’ (for example, ‘The State of Queensland acting through the Department of Main Roads and Transport’).
    Here are sometricks of the trade for
    respondents
    to look out for:
  • Ensure the claimant listed on the payment claim and the adjudication application are the sameand is the person or organisation you entered into the construction contract with. If the claimanthas incorrectly identified itself on the adjudicationapplication this may be grounds to argue that the adjudicator should decide against the claimant on the adjudication application.
  • Although this goes without saying, ensure theperson you have contracted with holds a QBCC licence to perform the construction work to which the contractrelates. If the person does not hold the appropriate licence, they cannot usethe adjudication process. You won’t find this edict in the BIF Act. It is a rule established by the Queensland Court of Appealin 2006.
    Application Form
    The ApplicationForm is broken up into 11 parts. Ensure you complete all 11 parts and fill outall details (especially those with an asterisk). If you, or the
    respondent
    , are represented by an agentor solicitor, ensure you complete part 2 and 4 of the Application Form.
    Ensure you include the:
  1. contract and project details;
  2. payment claim details; and
  3. payment schedule details (if applicable).
    TheApplication Form must be served on the
    respondent.
    If you do not serve your
    adjudicationapplication
    in accordance with your contract and/or the applicable law,your
    adjudication application
    may beinvalid. For more information on service, you can view our previous article
    here
    .
    You will alsobe required to provide proof of service of the
    adjudication application
    on the
    respondent
    to the
    adjudicator.
    If you emaila copy of the application to the
    respondent
    provide a copy of that email to the
    adjudicator
    (that is, if service by email is permitted)
    .
    Alternatively, if you mail or personally give a copy of the
    adjudication application
    to the
    respondent
    , ensure you havedocumentation evidencing this.
  1. Make your adjudication application within the required time frame.
    Your
    adjudication application
    must be filed before5:00pm on the last
    business day
    ofthe period permitted. If it is even a minute late, your application will be outof time. If you are attending a QBCC office to personally file the application,we suggest you attend with considerable time to spare.
    Notably,if you intend to deliver your
    adjudicationapplication
    in person to a QBCC regional office (that is any office otherthan Brisbane), it is recommended you deliver your application no later than 4:00pmto allow it to be processed and acknowledged as received by the Registrar before5:00pm on the same
    business day
    .
    Whateveryou do, don’t send the
    adjudicationapplication
    by post unless you have ample time left to spare in the timeallowed. The post can be unreliable. We also recommend that you do not relyupon a courier. There are specialised process servers available to both lodgethe
    adjudication application
    with theRegistrar and serve a copy upon the
    respondent
    ,if required.
    Also,don’t forget that you can, depending upon the size of the files, lodge the
    adjudication application
    on-line. Wegave you the link to the on-line form above. Note that although you may belodging the
    adjudication application
    on-line, it must still be received by the
    Registrar
    before 5pm on that last
    business day
    . When lodging on-line, youwill receive an acknowledgment of the time and date when the upload wascompleted (i.e. the adjudication application lodged).
    See ourprevious article
    here
    for more detail on the required time frames.
  1. Accurately identify the payment claim and payment schedule (if any) to which the adjudication application relates.
    Youmust include a copy of those documents with your
    adjudication application
    .
    Ensureyou include a copy of:
  1. The relevant constructioncontract (if any);
  2. The paymentclaim and all included annexures;
  3. The paymentschedule and all included annexures; and
  4. Submissions proving your entitlement (to be the subjectof our next article).
  1. Pay the correct fee.
    The Building Industry Fairness (Security of Payment) Regulation 2018
    (“
    BIF Regulation
    ”) prescribes the fees payable by the
    claimant
    for an
    adjudication application
    which range from $57.35 to $5,737.60 depending on the amount of the
    payment claim
    . For example, if your
    payment claim
    claims $150,000, the applicable fee is $401.65. This fee does not include the
    adjudicator’s fees
    which are payable upon notice from the
    adjudicator
    that the decision has been made. To find out what you will need to pay, details of the fees are found on page 7 of the
    Application Form
    or in Schedule 2 of the BIF Regulation; and
  1. Include submissions in support of your application for the adjudicator’s consideration, if you so wish (which we strongly suggest you should). We discuss the do’s and dont’s of submissions in our next article.

After the Adjudication Application is Filed

After a claimant files an adjudicationapplication the registrar must,within four (4) business days afterthe application is received, refer the application to an eligible adjudicator.The adjudicator then has a furtherfour (4) business days the accept orreject the referral.

Upon an adjudicator accepting the application, the claimant must provide the adjudicator with proof of service of the application on the respondent. Correspondence with the adjudicator should be done through the adjudicator’s nominated agent. The adjudicator will advise you of those details in the notice of acceptance. Further, it is recommended that any correspondence to the adjudicator is copied to the other party to ensure procedural fairness is afforded. After the adjudicator has accepted the application, it is not appropriate to correspond with the QBCC registry until after the decision is made.

An adjudication application may be withdrawn on two occasions:

  1. Ifthe claimant has given written noticeof discontinuation to the adjudicator andrespondent; or
  2. Ifthe respondent, before the adjudicator has decided the application,paid the claimant the amount statedin the payment claim the subject ofthe adjudication application. It isup to the claimant to notify the adjudicator as soon as practicable thatthe adjudication application has beenwithdrawn because of payment.

If an adjudication application is withdrawn, the adjudicator will still be entitled to be paid his/her fees forconsidering the application up until the date of withdrawal.

Key Takeaways:

  1. Carryout a search of the company name and the ABN number that appears on thecontract. You can do a free business name details check in the ASIC businessname register. You can also obtain company extracts and business name extractsfor a fee. An ABN search on ABN lookup may also be helpful in determining thecorrect business entity. It should also determine whether there is a trust inplace.
  2. It is vital that any application is served inaccordance with legal requirements for proper service. That will depend onwhether you are serving an individual, partnership or corporation. See ourprevious article for how to effect proper service. Note, you may need to allowyourself extra time to effect service if the other party is interstate.
  3. Time frames are vital.
  4. Complete all parts of the Application Form. An incomplete Application Form could resultin your application being deemed invalid.

Staytuned, coming up next is what to include (or not include) in your adjudication application.

Working as an adjudicatormakes it easy to see where people go wrong. With more than 38 years’ experiencein the construction industry and as an adjudicator in Queensland and otherStates and Territories for more than 13 years, Active Law’s Paul Hick is veryfamiliar with the practical, financial and legal difficulties contractors facegenerally as well as with the adjudication procedures in the BIF Act. Paul regularly assists claimants and respondents with the adjudication process and indeed in many othermatters requiring expertise in construction law.

Formerly employed by theQBCC, Emma Ward has invaluable insight into statutory regulation and canswiftly identify your rights and obligations to ensure you comply with yourstatutory and contractual obligations.

So, whether you require assistance with a payment claim and adjudication application, a payment schedule and adjudication response, other forms of dispute resolution including litigation, or the drafting of your own contracts to better protect you, Active Law are well placed to help to achieve your best position possible. To make or defend a claim under the BIF Act, or for any matter requiring expertise in construction law, we are only a phone call away.

Disclaimer:
Reliance on content the material distributed is general information only. The information supplied is not and is not intended to be, legal or other professional advice, nor should it be relied upon as such. You should seek legal or professional advice in relation to your specific situation.

Share this post